The last month has been spent getting utilities in place. The electrical was run and the plumbing installed, including a manabloc which allows me to turn of individual fixtures or areas of the house.
In addition, my brother Kevin has come several times to help me run the networking cables-just two more CAT 6 lines for phish into interior walls.
While waiting for the 4-way (framing, roofing, electrical and plumbing) to be approved, the focus has been on the exterior. The concrete work in the garage and door landings was poured.


I've also started on the on the landscaping. I've started on the fence and the sitting-height retaining wall which wraps most of the side yard now.